Building permits in Caledon

Which projects need a Town of Caledon building permit, what to check first, how to apply online, the 2026 fees, how long review takes, and how inspections work.

Summary

The Town of Caledon accepts building permit applications online only, as PDFs through its web form, and reviews them against the Ontario Building Code, the zoning by-law and other applicable law. Most fees are set by floor area in the 2026 Fees By-law, with a $193 minimum for most permits. Building Services answers questions at 905-584-2272, ext. 2233.

Last verified

Administered by the Town of Caledon Building Services division, under the Chief Building Official. Every answer below was checked against its source on November 27, 2026; the source is linked under each one.


Do you need one, and what to check first

When do I need a building permit in Caledon?

For most construction, yes. The Town lists new buildings and additions (including garages, sunrooms, porches and decks more than 24 inches off the ground), removing structural walls or enlarging windows and doors, finished basements and basement apartments, sheds of 15 square metres or more, other accessory structures over 10 square metres such as sea cans and detached garages, new or changed plumbing and heating, septic systems, demolition, and any change in how a building is used, even with no construction.

The Town says the owner is fully responsible for getting the permits the Building Code requires; skipping one can mean delays, legal action or removal of the finished work.

Source: Town of Caledon, Building Permits

What work does not need a building permit?

The Town's list includes decks no more than 60 cm (24 inches) above grade at any point, adding or replacing insulation, replacing windows or doors in the same opening, replacing a furnace or boiler in a house, installing air conditioning, a gas fireplace or a hot water tank in a house, replacing plumbing fixtures, basement waterproofing repairs, private retaining walls not open to the public, and a small storage shed that meets the size and use conditions.

Even when no permit is needed, the Town says zoning clearance is required before any new project starts.

Source: Town of Caledon, Building Permits

What should I check before applying?

Start with zoning: the project must meet Comprehensive Zoning By-law 2006-50, and Planning can be reached at ext. 7338. A new or changed driveway entrance needs road access approval from the Town, Peel Region or the Ministry of Transportation, depending on the road. The Town names four outside bodies whose approval may also be needed: the Toronto and Region Conservation Authority, Credit Valley Conservation, the Niagara Escarpment Commission and the Oak Ridges Moraine rules.

New houses and redevelopment may also owe development charges and cash-in-lieu of parkland, which are handled by Finance and by Planning and Development Services.

Source: Town of Caledon, Building Permits

My property is on a septic system. Does that change anything?

Yes. Where there are no sanitary sewers the owner is responsible for sewage disposal, and installing a new septic system, or making changes on the property that may affect one, needs a building permit. The design must be based on a soils analysis, installers and designers must hold a provincial licence, and a Town inspector has to approve each stage before any part of the system is covered.

The Town's 2026 fee for a new or replacement septic system is $564, and a repair that does not replace the bed is $282.

Source: Town of Caledon, Septic Systems


Applying and paying

How do I apply for a building permit in Caledon?

Online only. Pick the project guide on the Town's Building Permits page, prepare the drawings and forms it lists (usually the Province's Application to Construct or Demolish, a checklist, and a Schedule 1 designer form if a designer drew the plans), and upload everything as unlocked PDF files through the Town's web form. Each attachment field takes one file, all files together cannot exceed 30 MB, and file names cannot contain special characters.

Drawings must be to scale, fully dimensioned, signed and dated; the Town posts a sample drawings package and says hand sketches no longer meet its standard.

Source: Town of Caledon, Building Permits

How much does a building permit cost in 2026?

Most permit fees are a rate times the floor area. For houses the 2026 rates are $18.12 a square metre for a new detached, semi or townhouse, $15.21 for a heated addition, $5.93 for a finished basement and $6.72 for a detached garage or shed. Decks, porches and basement walkouts are a flat $192 each, and demolishing a house is $321. The minimum fee is $193 for most permits and $321 for assembly, care, business, retail and industrial buildings.

Selected Town of Caledon building permit fees, 2026 (before HST)

Selected Town of Caledon building permit fees, 2026 (before HST)
WorkFee
New detached, semi, townhouse or duplex$18.12 per m²
Addition, heated$15.21 per m²
Addition, unheated$14.40 per m²
Finished basement$5.93 per m²
Detached garage, shed or accessory building$6.72 per m²
Interior alterations, residential$5.64 per m²
Deck, porch or basement walkout$192 each
Residential demolition$321 per building
New or replacement septic system$564
Minimum permit fee (most permits)$193

Table source: Town of Caledon, By-law 2025-105, 2026 Fees By-law, Schedule B Building Services

An attached garage and an unfinished basement are not counted in a house's floor area. Fees for work the schedule does not list are set by the Chief Building Official.

Source: Town of Caledon, By-law 2025-105, 2026 Fees By-law, Schedule B Building Services

When and how do I pay?

After the Town checks that your application is complete, staff contact you for the minimum fee, which is non-refundable; if it is not paid within 10 business days you must resubmit the whole application. For permits worth more than $5,150 you can pay the full fee at application or half then and the rest when the permit is issued. No more than $5,000 can be charged to a credit card on one application.

Source: Town of Caledon, By-law 2025-105, 2026 Fees By-law, Schedule B Building Services

How long does the Town take to review an application?

Once a complete application is paid for, the Building Code timeframes apply: 10 business days for a house, tent or demountable stage, 15 for small buildings and additional residential units, 20 for large buildings and 30 for complex buildings. Incomplete applications are not processed and are not held to these timeframes, and resubmissions have no guaranteed review time; the Town says each one can add two weeks or more.

Source: Town of Caledon, Building Permits


Inspections, changes and refunds

How do I book a building inspection?

Through the Town's online booking form, by phone at 905-584-2272, ext. 4174 (Monday to Friday, 8:30 a.m. to 4:30 p.m.), or by emailing the inspection request form to building.inspections@caledon.ca. Give at least 24 hours' notice: requests in before 1 p.m. can be inspected the next day, subject to availability, and later ones go to the second day after. Inspections take place weekdays from 9 a.m. to 4:30 p.m.

Have your permit number, address, inspection type and the on-site contact ready. Approved drawings, printed to scale, must be on site, and work covered up before it was inspected may have to be opened.

Source: Town of Caledon, Building Inspections

Which inspections will my project need?

The Town's list of mandatory stages runs from footings and backfill through drains, plumbing and HVAC rough-ins, framing, and insulation and vapour barrier, to plumbing, HVAC and building finals; septic systems add base-cut, pre-backfill and final inspections. It is the builder's or owner's job to call each one in. For a new house, the final inspection leads to an occupancy permit and needs the Electrical Safety Authority's final certificate.

The Town does not do electrical inspections; those are done by the Electrical Safety Authority.

Source: Town of Caledon, Building Inspections

How can I check the status of my permit?

The Town publishes a Building Permit Status map showing active permits and those that have been closed or cancelled. It is updated every 24 hours, with information as of the previous business day, so you can follow your application without calling Building Services.

Source: Town of Caledon, Building Permits

How do I revise, transfer or cancel a permit?

All three are done by email to Building Services. A revision is for a change in scope after the permit is issued: send the revision form with updated plans, the changes clouded. A transfer is needed when the property changes hands while a permit is active or under review, using the same form with the new owner's details; the 2026 transfer fee is $192. To cancel, send a letter signed by the owner with the reason, permit number, address and permit type.

Source: Town of Caledon, Building Permits

Can I get a refund if I cancel?

Partly, and never on the minimum fee. The 2026 Fees By-law refunds 85 per cent of the fee if only administration was done, 70 per cent after zoning or Building Code review, 50 per cent after both, and 45 per cent once the permit is issued but before any field inspection, less 5 per cent for each inspection done. Nothing is refunded if the refund would be less than the minimum fee, or a year after application if the permit was never issued or acted on.

Source: Town of Caledon, By-law 2025-105, 2026 Fees By-law, Schedule B Building Services

What happens if work starts before a permit is issued?

It costs more. The 2026 Fees By-law adds a charge for work started early, set at $150 or a share of the permit fee: 50 per cent for work begun before applying, 25 per cent for work begun after applying but before issue, 10 per cent for work not built to the approved permit, and 100 per cent where the work is already complete. Town inspectors also investigate work done without a permit and can require that it be removed.

To report suspected unpermitted work or a Building Code violation, contact Building Inspections with your name, address, phone number and the property's address; the Town does not accept anonymous complaints.

Source: Town of Caledon, By-law 2025-105, 2026 Fees By-law, Schedule B Building Services

Sources

Every factual claim above traces to one of these documents.

  1. Town of Caledon

    Building Permits

    Retrieved November 27, 2026

  2. Town of Caledon

    Septic Systems

    Retrieved November 27, 2026

  3. Town of Caledon

    By-law 2025-105, 2026 Fees By-law, Schedule B Building Services

    Retrieved November 27, 2026

  4. Town of Caledon

    Building Inspections

    Retrieved November 27, 2026